Crews were hard at work in late August installing conductor (wires) on the transmission structures on the southern portion of the project. Construction on the lines south of the Zoo Interchange will continue through this fall and winter and will be placed into service this winter.
On the Western
Milwaukee County Electric Reliability Project, crews are using wooden
construction mats to protect the ground and wetlands from damage by heavy
machinery as they work to install transmission foundations and structures along
the portion of the line that runs along Underwood Creek Parkway.
Duct instillation work for the underground portion of the line should
be completed in September. Foundation work and pole setting for the
overhead portion of the project will continue this fall, with wire stringing
occurring in late fall. The project is on track to be placed into service in spring
2015.